Activities regarding construction of RC piles (up to ф600)

  • Transportation of machines and materials to the construction site;
  • Preparation of access site/road for the drilling rig machines with weight up to 50t (responsibility of the Contractor);
  • Screw drilling with or w/o casing (depending on geology conditions) – depth according to design project;
  • Installation of rebar sets;
  • Concrete works;
  • Casing removal.

Installation of driven piles – steel sections

  • Transportation of machines and materials to the construction site;
  • Preparation of access site/road for the drilling rig machines with weight up to 50t (responsibility of the Contractor);
  • Pile driving according to design project